Project Description

Comprehensive Monitoring, Inspection and Construction Control, of the construction project of the South Terminal. Tocumen International Airport S.A.

The plan of the Expansion program of the the Tocumen International Airport, consists of the realization of Studies, Designs and Construction of the following elements:

  • New Building South Terminal of the Tocumen International Airport (stage 1) with a built area of 95,000 m2, including
  • 20 new boarding gates with movable bridges
  • Electric substation and connection to the existing substation in Tocumen property of ENSA
  • Baggage Handling System (BHS9)
  • Special systems

o CCTV and Access control

o FIDS

  • River Tocumen diversion works
  • New control tower
  • Aircrafts´ taxiway and interconnection with existing ones
  • Aircraft parking platform
  • Expansion of the fire extinguishing system (FES)
  • Escalators and lifts
  • Drainage, electricity, voice and data, telephony, wi-fi network
  • Air conditioning, Supply of drinking water
  • Boulevard vehicular access from the South Corridor
  • Viaducts interconnected with the South Corridor
  • Parking of Vehicles
  • Necessary connections with the existing terminal
  • Incorporation of the distribution network of aviation fuels for the 20 new aircraft positions
  • Enlargement of the taxiways and aircraft parking apron of the existing terminal
  • Expansion of water storage system
  • Water distribution system
  • RESAS establishment in existing runways, adequacy of strips on the new runway and on the existing runways
  • Maintenance and construction of rain channels
  • Restructuring, repair and maintenance of airport structure pavements

The role of CEMOSA

  • Responsible of the supervisión of Flight Field
  • Technical Control of the work
  • Facility Control