Project Description

CEMOSA in UTE (Temporay Joint Venture) with the company EPTISA has been awarded the Consultancy and Technical Assistance contract for the Project control and actions in the High Speed line Monforte del Cid-Murcia.

The section of Monforte del Cid-Murcia is a part of the high-speed Madrid-Castilla La Mancha-Comunidad Valenciana-Region of Murcia line, and its commissioning will allow to connect  Elche, Vega Baja and Murcia to the high-speed network.

It has a length of 61.7 km, of which 46.2 km and is located in the province of Alicante and the remaining 15.5 km in Murcia. This length will increase to 69 km including the underground section of the Murcia and Barriomar Station.

The section starts at km 461,356 at the La Encina-Monforte del Cid-Alicante junction where the fork between Murcia and Alicante takes place. Between this node and the PAET of San Isidro the line will be exclusive for passengers and the platform has been arranged as a double track with an international width. This provision is maintained until El Reguerón, in which the LAV is made up of a UIC wide track and has a mixed width (with three wires). From there to Murcia are the sections that are currently under construction where the LAV will also have a UIC and a mixed route and will end in Murcia including the integration of the AVE in Murcia (underground access), as well as the underground Murcia station.

The object of the Technical Assistance is the control of the necessary projects that allow the commissioning of the line. In addition, the UTE will participate and support ADIF in all the processing and files necessary for the commissioning of the line.

Role of CEMOSA

CEMOSA as a 50% member of the UTE, will provide personnel to the technical assistance team as well as provide support from its central services, following the internal quality guidelines of the company and Adif.