The scope of works that have been contracted by GACM, for MEXICO CITY’S NEW INTERNATIONAL AIRPORT GROUP, are to perform technical supervising and management of the construction, including monitoring, quality control, control and commissioning of the electrical distribution of Medium Voltage (23 kV), that is composed by 13 core rings and 48 power substations, with an overall power demand of 230 MVA, 750 km of backbone cable and 285 Km of fiber optics cable for control.

The works have a time span of 3 years, beginning next June.

Overall budget of the works is 3.600.000.000 $MN, or 200.000.000 US$

Cemosa will lead the Supervising team to one of the main construction companies of the Mexico, deploying more than 10 technicians of the highest skills at the working site.

Links of Interest:

Mexico City’s new International Airport
NAICM in Wikipedia
NAICM in Twitter

The Economist Mexico